From this month, Ji'nan's personal power generation can be applied for direct sale to the power grid.
http://www.dzwww.com/shandong/sdnews/201303/t20130304_8070399.htm
Ji'nan Daily reporter Wei Gaofeng
since this month, Ji'nan citizens can not only use new energy, such as solar energy and wind energy, but also can be sold to the national grid directly according to the price of transmission. Today, the Ji'nan power supply company has disclosed that as a subsidiary of the State Grid, they have accepted the application of personal distributed power grid service since this month.
What are the conditions for individual power generation to be incorporated into the national grid? A technical staff member of Ji'nan power supply company said that, according to the requirements of the national grid, the distributed power source invested by the citizens or units should be located in the State Grid, which must be located near the user, the power generation can be used in place, the voltage level of 10 thousand volts and below, and the capacity of a single network of 6 megawatts.
according to the grid connected service program issued by the State Grid, the Ji'nan citizens or units should first apply to the Ji'nan power supply company for the construction of distributed generation projects. The Ji'nan power supply company issued a confirmation form of the access scheme and an access letter. After the project owner confirmed it, the selection of the design construction unit and the product supply list Position and so on. After the completion of the project, the Ji'nan power supply company has accepted the acceptance, installed the electric energy metering device, signed the purchase and sale contract with the project owner or the power user, and the network dispatching agreement. After debugging, it runs directly to the net. Can
users who have previously installed distributed power connect to the network? The power supply technician introduces that whenever he meets the requirements of grid connection, he can apply to the Ji'nan power supply company at any time to sell the rich electricity to the power grid.
State Grid has publicly promised to provide free gateway metering device and electricity meter for power generation measurement for distributed photovoltaic power generation and wind power projects. No system reserve capacity fee is charged; application for grid application is not more than 60 days.
personal power generation to the State Grid, what electricity price shall be settled for settlement? According to the power supply department, the amount of electricity generated by individuals or units should be settled separately according to the Internet and the next network. At present, in Ji'nan, there are two kinds of implementation of the distribution price of distributed power supply, one is not the scattered users who have not obtained the national formal project, and 0.4469 yuan per kilowatt hour; the other is to obtain the official status of the state, and the price of the national related policies.
the power supply department further explained that the second type of pricing method is aimed at the distributed generation project enjoying the national tariff subsidy. Ji'nan citizens or units must apply for approval to the municipal development and Reform Commission for the purpose of generating electricity subsidies. The power supply department provides subsidies, measurement and settlement services according to the approval of the price department. Prior to
, the state has introduced a series of supporting policies to encourage the development of new energy sources, including distributed generation. Distributed power supply includes solar energy, natural gas, biomass energy, wind energy, geothermal energy, ocean energy, and comprehensive utilization of resources. In terms of natural conditions and geographical location of Ji'nan, distributed photovoltaic generation is the most suitable investment for individuals and units.