Re: Ji'nan rail transit construction Seven Mile fort and other sections of the longest closed two and a half years.
from March 25, 2017 to February 28, 2018, the closed construction of the motorway of Zhu Shun Road and Xin Zhu Road, in the meantime, the motor vehicles bypass, pedestrians and non motor vehicles on both sides of the traffic, bus vehicles bypass.
Lishan North Road Station
the first stage: from March 25, 2017 to May 6th, the construction of some sidewalks to the south side of the North Garden Avenue (about 50 meters west of the Lishan Road), the number of lanes in the west to the East is not The BRT lane is closed to the north side of Beiyuan Street (East to the north of the Lishan Road), and the east to West BRT Lane moves northward.
second stages: from May 7, 2017 to November 30, 2017, some roads were closed to the southern side of the North Garden Avenue (about 50 meters west of the mountain road). During the period, the west east 5 lanes were changed to 3 lanes, pedestrians Mixed with non motor vehicles; from May 7, 2017 to July 5, 2017, the closed construction of some BRT lanes on the north side of Beiyuan Street (East Road to Lishan North Road) was continued.