Ji'nan's four largest project, the new water source, is expected to drink the Changjiang River in November.
Qilu Evening News
water diversion project of Yufu River Reservoir in Yufu River, which is being carried out in pipeline.
6 from 20 to 21, reporters follow the spring environmental century activities report group visited the Yangtze River water related projects in Ji'nan. The reporter learned that the first phase of the East Route of the south to North Water Transfer Project will be opened to the whole line in the third quarter of this year, the fastest can come to Shandong in September, but only in the main line of water transportation. As the south to North Water Transfer Project is completed by the end of September, it can be completed by the end of September, so that the citizens of Ji'nan can use the Changjiang River to wait until November.
the completion time of
of Yuqing Lake diversion project: completed by the end of September 2013, with water diversion conditions.
engineering significance: the Yuqing Lake drinking water project is the key project of the construction of the modern water network in Ji'nan and the construction of the water ecological civilization city. The implementation of the project can realize the connection between the two major water sources of the Jisun trunk and Yuqing lake water reservoir, and the high quality Changjiang Water and the Yellow River water diversion can be introduced into the Yuqing lake reservoir, and the change can be changed The Yuqing lake reservoir only depends on the condition of the single water source of the Yellow River, which improves the reliability and water quality of the water supply of Yuqing lake, and improves the water supply level of the city. In addition, the gate is reserved for the water separation of the wetland, which can meet the needs of the ecological water use of the wetland, improve the ecological environment of the western urban area, and promote the healthy development of the economy and society.
Yu Fu Hushan Reservoir
water diversion project
completion time: planned to complete the pipeline paving task in mid July this year, before the end of the year to realize the test water, the completion of the whole line before the end of May 2014.
engineering significance: the water transfer project of the hushushan reservoir in Yufu river is an important part of the continued construction of the urban area in the eastern part of the south to North Water Transfer Project in Ji'nan. Through the diversion of Changjiang River and the Yellow River water to the reservoir of supine tiger mountain, the project can give full play to the storage function of the reservoir and realize the interconnection and joint operation of the Changjiang water, the Yellow River water and surface water. It can not only provide reliable water supply for the urban area, but also connect the major water systems in the southern mountainous area, and build a "six horizontal eight longitudinal and one surround spring" The modern water network system of the city provides key support.
in addition, the project will also play an important role in ensuring the continuous spraying of spring groups. On the one hand, the project can recharge and supplement the source in the dry period, directly recharge the groundwater in the urban area and ensure that the spring group does not break the flow; on the other hand, the water replacement project is relocated in the spring field, and the water is replaced by the groundwater from the groundwater to the surface water. We should effectively reduce the amount of groundwater exploitation and optimize the allocation of water resources.
Tianshan irrigation district and Ji Ping main canal
connectivity project
completion time: at present, the main works of the project have been completed and passed the inspection.
engineering significance: the connection project of Tianshan irrigation area and Ji Ping trunk canal has been formally replenish to the Xiaoqing River in April 5, 2013. To more than one month in May 8th, the water supply of about 15 million 900 thousand cubic meters has greatly improved the environment of the Xiaoqing River.
this project is to use jisping canal for the Yuqing lake water reservoir and the Xiaoqing River to supplement the water reservoir in the south to North Water Diversion Project, in order to reduce the operation load of the subsank sand pool in the Yuqing lake water reservoir, improve the water supply guarantee rate and water quality, and improve the water quality of the Xiaoqing River.
East Lake reservoir
completion time: at present, the East Lake reservoir has been basically completed, with water storage conditions.
engineering significance: after the completion of the reservoir, 40 million 500 thousand cubic meters of water can be supplied to Ji'nan city every year, and 17 million cubic meters of water supply to Zhangqiu City, which can effectively relieve the tension of local water resources.
the East Lake reservoir is responsible for the allocation of the trunk line project to the Yangtze River water in three cities of Ji'nan, Binzhou and Zibo. The East Lake reservoir after completion will be integrated with the water network planning of Ji'nan to connect the water supply network in East China, effectively solve the water shortage in the eastern part of the city and the water use in the river landscape, alleviate the current situation of overexploitation of the groundwater in the eastern region and optimize the allocation of water resources.