Ji'nan R3 line Dragon Olympic Station to the Olympic center west station interval double line
Qilu Evening Newspaper - Qilu one point author: Zhao Xia ye
the right line of the Dragon Olympic section is 968 meters long and constructed by shield method. The development of No. 10 shield machine was launched in January 19, 2018 from the Dragon Olympic Station and received at the West Olympic Station. From the line of the long Austrian station on the interval line plane, the line section of the radius 1000m curve section and the radius 800m line are laid along the Austro West Road, and the straight line enters the west station of the Olympic Center. The distance between 13 to 14m and interval tunnel depth is 13.24 ~ 19.66m, which mainly passes through the weathered limestone strata in the whole section and passes through the filled karst cave many times. The maximum slope of the interval line is 27.amp; permil, in the R3 whole line of Ji'nan metro, only the project interval is located in this kind of stratum. After the start of
shield machine, the shield construction is faced with serious damage, low push efficiency and opening switching frequency under normal pressure in high strength hard rock stratum With the big rate and difficult control of the shield attitude, the whole interval shield construction has been opened 451 times at normal pressure and 45 times at normal pressure, and the average of every 16 ring should be replaced once, which greatly affects the construction progress.
under the correct leadership of the group company, the third pipe centers hold several expert meetings and production scheduling meetings, constantly study and adjust the parameters of the shield tunneling, adjust the modified ratio of the residual soil, and find out the rational construction on the basis of the wear law of the hob in the hard rock formation, so as to ensure the driving efficiency of the shield machine. At the same time, in the process of construction, 24 hours uninterrupted monitoring, through real-time measurement of ground settlement, information monitoring and other measures to effectively control the driving parameters, reasonable construction of the site construction organization. It lasted for 164 days, and the 798 rings were drifting and assembled. They were worn through ten roads, the Austrian West Road and the surrounding important pipelines.