Ji'nan trolleybus network "five rings and nine shots" has been launched in four years.
Shandong commercial newspaper
yesterday, reporter learned from the Ji'nan Transportation Bureau, from the Asia Development Bank East Asia Transportation Bureau, the Asian Development Bank The relevant experts of the CDIA Asian urban development center, conducted a survey in Ji'nan, conducted a survey on the construction of a green modern tramcar Bus Demonstration Project in Shandong Spring City in Ji'nan by using the loan of the Asian Development Bank. At the same time, the project was formally launched and signed the framework agreement. If the research is successful, the project will receive a loan of 990 million yuan, while the total investment plan of Ji'nan will be RMB 2 billion 400 million yuan.
reporters learned that, at present, the modern trolley bus construction project in Ji'nan has been successfully included in the 2016-2018 year project plan of the ADB loan. The project is centered on the construction of modern tramcar network, including the construction of modern tramcar network, the upgrading and upgrading of the bus platform, the construction of the supporting infrastructure, the purchase of vehicles, the transformation of the bus intelligent system, the upgrading of the traffic management and the establishment and management of the capacity of the institutions. The project will build a green modern trolleybus network with a total length of 201.4 km, effectively alleviate urban traffic congestion and reduce air pollution. It is understood that Ji'nan will build five trolley nine trolleybus network. It is predicted that when all the tram lines are opened in 2020, the daily traffic volume is about 1 million 580 thousand people, accounting for about 60% of the total number of passenger flow in the main city area (without rail traffic).
behind the curtain
the environmental tramcar does not touch the line and can run
generally speaking, the construction of tramcar network has two blocks, one is to erect a touch line network, and the two is the tram vehicle after its braid.
in the future, the provincial capital is expected to upgrade the BRT system to the tramcar BRT system for the existing North Garden Avenue, the Second Ring East Road and the Second Ring West Road Elevated Road, while the replacement of the BRT diesel vehicle is a modern tramcar vehicle. Under the viaduct transformation, the fixed line network of pier column can be utilized to make full use of the space resources under the bridge, which can save construction costs and stealth the tram net under the viaduct. On the other hand, the side roads are installed on both sides of the municipal roads, and the rods and lampposts are used together.
the future braid new tram is also more worthy of expectation. The online charging type dual source trolleybus will be adopted. With the power battery, tramcars can run off line. When the vehicle runs on the touch line, the wire network recharges the power battery to the power battery while the trolley is running in the area without the touch line network. The power battery power the motor to drive the vehicle. The dual source trolleybus overcomes the problem of the low flexibility of the traditional trolleybus which relies entirely on the touch line network.
in the 1361 modern trolley cars planned to purchase. 18 meters articulated trolley bus 1053, 12 meter trolley 308. In the vehicle selection and the technical ability of the domestic bus manufacturers, the 12 meter tramcar adopts a 18 meter tramcar with a measure production of a dual source and 18 meter hinged modern tramcar. In addition, the information facilities set up the substation monitoring system, with the intelligent monitoring center as the center, through the network to the trolley trolley substation data and image remote monitoring, reduce manual inspection.
the total length of 308 km / >
will achieve zero pollution and zero emission
according to the development plan of the tramcar of Ji'nan Public Transport Corporation. By 2020, the modern tramcar network with five rings and nine shots will be built, the power supply touch line network is set up 179.1 kilometers, the total line length is 3 08 kilometers. At present, there are 4 trolleybus lines on 101 roads, 102 roads, 103 roads and 104 roads in Ji'nan, which has been with the provincial cities for nearly 40 years. The planning of the Nine Rings means that more streetcar lines will be opened up in the future.
according to the plan, the first phase of the trolley bus project (2014-2015, due to the lack of funds and so on) has been implemented, and a modern two trolley bus network has been built. One ring refers to Beiyuan Street - the Second Ring Road East - the Second Ring Road South - the Second Ring Road West. The two shot refers to the flyover, the west railway station and the Wei Wei Kuang Shan flyover. In the first phase of the project, the existing BRT system is upgraded to the tramcar bus (BRT) system, and the existing BRT diesel vehicles are replaced by the existing tramway vehicles.
two phase project (2016-2020), the construction of modern trolley bus network with five rings and nine shots, the total length of power supply contact line reaches 179.1 km. The five rings refer to the North Garden Avenue - the Second Ring East Road - the Second Ring South Road, the Second Ring West Road and the Beiyuan Street - weft two road - through the ten road - Second Ring West Road, the North Garden Avenue - the second ring road - through the ten road - two road, the Beiyuan Avenue - the Lishan road - the ten - Wei - twelve Road, the Beiyuan Avenue - Phoenix Road - Second Ring Road - Second Ring Road. Nine shooting refers to North Garden Street - Industrial North Road (Phoenix Road - West Passenger Station), four road - Jiefang Road - Industrial South Road (Fenghuang road - Xin Xi Road), South Xin Zhuang West Road - seven road - Peace Road (the Second Ring East Road - Second Ring Road), the ten road (Xing Village Flyover West Passenger Station), the Second Ring West Road (Dawei Beijing Shanghai railway bridge), latitude twelve Road (Second Ring North Road nine Qu), Wei two road (Kou Kou - Nan Kang), Second Ring Road East (high wall Wang Yanshan overpass), Fenghuang Road (industrial North Road - tourist road).
associated link
will build tramway ring corridor
according to Ji'nan municipal government work report, this year Ji'nan will speed up urban construction, new and optimized adjustment of 20 bus lines, construction of the two ring tram ring corridor, to improve the share rate of public transportation. On the two ring tramway ring corridor, the ring corridor mainly refers to the North Garden Street.Amp; mdash.amp; the mdash Second Ring East Road.Amp; the mdash.amp; the mdash Second Ring South Road.Amp; mdash.amp; the mdash Second Ring Road.