Ji'nan part of the housing reform project has a preliminary timetable.
Shun Net - Ji'nan daily
Ji'nan? A lot of people are talking about this problem. Since 2007, Ji'nan has reformed 38 centralized shanty towns. A few days ago, journalists followed the staff of the Ji'nan old city development investment group group to visit the city part of the city; the project, the project, the Ji'nan second automobile reloading plant project, which was implemented by the old city group of Ji'nan and the government of the Lishi District, has been completed and started yesterday. To move back, more than 240 residents will be rehoused for a period of three days.
in addition, the second medicine East, the second medicine North danger old house renovation project, the village transformation project in Wen Zhuang City have already entered the collection and removal end. As the last start of the continuous film shed modification area, most of the project in the Beijing University of Huai shawning area has entered the end of the end of the end of 2017; the railway station north field The station integration project and the new Quancheng building project are stepping up construction.
> Shandong Art Theater East Project: 4 resettlement buildings are completed by the end of next year
this project is located in the south side of Huayuan Road, the north side of the extension line of the grand North Road, the west side of the mountain road, the east side of the Garden Zhuang Road, the first phase of the Lu Yi theatre, the total area of about 157.8 mu, the planning and construction land 122.55 mu, moving 1253 households. 4 houses are planned and built in the resettlement plot. At present, 3 buildings have been capped and another building is built to more than ten floors. It is planned to be completed by the end of 2017. After the transformation, the residential building area of the residents is up to 93 square meters from 73 square meters before the reform. The kindergarten will be built in the project.
railway Career Technical College project: 6 resettlement buildings are completed by the end of next year
this project is located in the lower region, the east to the mountain road, South to the New South Road, the west to Shandong Road, the north to Jiefang Road, the total area of about 262 mu, 919 households. 1100 households can be housed in the resettlement house. At present, 6 resettlement buildings have been built to 3 floors on the ground, and are planned to be completed by the end of 2017. After the transformation, the average area of residential area increased to 77 square meters to 109 square meters.
2 steam reform project: the resettlement area is building
this project is located in the east of peace road, east to Erhuan East Road, West to meadow East Road, South to the east of peace road, and north to the dorm of the Mining Bureau. The project is divided into A and B plots, and the area of project planning and construction land is about 63.45 mu. About 256 households are required to be levied. The project involves 270 sets of resettlement houses. At present, 3 11 story resettlement buildings have been completed, and the resettlement of the New District of Dianxin park on 28 28 days has been carried out for a period of three days. The kindergartens in the community have been built.
Nan Xin Zhuang, official tie camp renovation project: Guan Ying camp primary school delivered
nine years old school and the young care project is located on the south side of Nan Xin Zhuang Street, and the east side of South Xin Zhuang West Street. Among them, primary and secondary schools altogether have 5 layers and 48 classes, and the kindergartens have 3 layers and 8 classes. At present, the foundation of the kindergarten is completed, and the construction of the 1 layer structure is prepared. The school is carrying on the basic construction. The project is now stepping up construction and is scheduled for completion in June 2017.
official camp primary school, nursery project: ending stage
located on the west side of Tiancheng Road, Baohua Street North. Among them, there are 5 classes and 30 classes in primary schools, with 3 classes and 12 classes in kindergartens. The project uses precast external walls, interior walls, floors and staircase precast materials, construction industrialization construction technology to carry out the construction. The project started construction in December 2015 and is scheduled to be completed before the end of July 2016. At present, the project is being decorated.
North locust area project: 9 buildings can be set up 3894 households
north to latitude eleven, West to weft Road, West to weft Road, south through the road, north to zimpu railway, the project in May 2010, the construction of the construction of housing in April 2014, the plan to complete the completion of the end of the year 2017. Construction of 9 resettlement housing, about 273 thousand and 600 square meters, can accommodate 3894 households. Supporting public works 23 thousand and 400 square meters, two underground garage 38 thousand square meters, 950 underground parking spaces, 405 parking spaces on the ground. The project will be equipped with 24 kindergartens and 48 classes of 1 primary and secondary schools.
Wen Zhuang village reconstruction project: first built and dismantled into the demolition and ending
Wen Zhuang section project located at the 104 National Road and the Second Ring Road South Road South about 1.2 kilometers, east to Ma Wu Zhai mountain, South to South Second Ring Expressway, West to 104 National Road, north to 104 National Road. The first construction and post demolition method, 8 1798 sets of housing construction in August last year, the construction of the main body is being carried out, some of the buildings have been constructed to the ground 8 floors; the project started in mid March this year, closed ring demolition work, now entering the demolition and closing stage.
the old city group to raise funds through multiple channels, by securing loans from financial institutions such as the state Kai bank and the support of the government's special funds to ensure the use of funds for the village reconstruction projects in the village of Wen Zhuang village. A total of 400 million yuan has been allocated to the Central District Demolition fund to ensure that the demolition funds are fully in place.
two drugs East and second medicine North critical room reconstruction project: the monetized resettlement rate reached 88%
the northern critical house reconstruction project is located on the east side of South Xin Zhuang Street in Huaiyin District, south of South Xin Zhuang Street. The project is a state-owned construction land. The land use is residential, with a total land area of about 2.32 hectares, and about 2.07 hectares of land can be planned for construction. The residential area is 35130 square meters, and the number of households is 779.
second drug east project is located on the east side of South East Street in Huaiyin District, south of Xin Zhuang Street. The project is a state-owned construction land. The land use is residential, with a total land area of about 0.78 hectares, and about 0.59 hectares of land can be planned for construction. The residential area is 13800 square meters, and the number of households is 224. The two projects of
issued a notice in March 1, 2016, signed a monetary compensation agreement in April 6th, and completed the housing selection in May 16th. As of June 23rd, 980 agreements had been signed, and the rate of monetization and resettlement reached over 88%.