Many new properties in the area of Ji'nan's Wang she people will be warmed up in January next year.
yesterday near the intersection of industrial North Road and dam Wang Road, workers are laying 1.2 meter thick heating pipeline reporter Qi Yuan
, "Hengda city this year Can you use the heat? "When will the east capital be warm?" Since the opening of the hotline, many owners of new developments in eastern Ji'nan have called. Most of these developments are concentrated in the area of Wang's area, and also a high degree of concern for Jinan Steel's residual heat radiation area. Will it be able to heat the heat on time this year? Yesterday, the reporter came to the area of Wang Shu Ren, and made a comprehensive interview about the preparation before heating. Reporter Liu Jianyu Gao Yulong
the west side pipeline has not started
yesterday morning, in the north of the industrial North Road and dam road junction, the reporter saw the roadside three or four meters deep in the tunnel, the workers are welding 1.2 meters thick pipeline. "These pipelines are 7 kilometers long and are expected to complete 5.8 kilometers east of the middle road in the near future, and 1.2 kilometers west of the middle road is still approved, and it is expected to complete the construction in January next year." Ji'nan thermal related responsible person said that the pipeline is mainly distributed in the toughened Road, the Austrian Middle Road, the Second Ring Road East.
at present, the Ji'nan thermal power project department has laid a pipeline of nearly 6 kilometers in the Wang Shi Shan area, and the 7 km line to be completed will meet the demand for the large-scale output of the heat source in Jigang.
the waste heat of Jinan Iron and steel company is still difficult to popularize
this year, it is understood that Han Cang District and steel city new park, like last year, will use industrial waste heat, but what heat source will other new residential quarters use? "We are stepping up the laying of pipelines to improve the Eastern Pipeline blank. The heating capacity of these pipelines can reach 6 million square meters, which is enough for Wang's area to use heat. But the official also said that although the pipe network has been laid up, the heat source of industrial waste heat is hard to enter more residents' homes this year.
the reporter has learned that Jigang has a large amount of industrial waste heat and blast furnace gas, which can provide 30 million square meters of heating capacity in the long term, and the heating area is 2 million 300 thousand square meters at present. This industrial waste heat is environmentally friendly and stable, but why is it difficult to promote it quickly? A person in the industry said that the heat source, heat exchange station, pipe network and other supporting facilities are involved in many departments and units. In addition to the waste heat of Jinan Iron and steel industry on the North Industrial North Road, a large amount of waste heat is available for the new urban area in the East, and the Tang Ye heat source plant is being built. The heat source in this area is relatively sufficient. However, the Ji'nan municipal government has proposed that the city heating should be marketed and diversified. It is bound to make the traditional heat source and the emerging heat supply heat to compete. However, in a market environment that is not completely open, it is bound to be full of complicated interests. Keep trying。
can not use the industrial waste heat to use the Yellow River heat source to save
for the use of Jigang waste heat and the pipeline has been paved to the door of the District, but the introduction of heat source has a variable, many residents are concerned, can the residential district be warm this year? The reporter learned that the district and units in need of heating in Wang's district are Hengda City, Wanxiang new day, Dong Du International, Jinan Third People's Hospital and so on. The heating demand is 500 thousand square meters. If the industrial waste heat fails to co-ordinate, what is the urgent need for heating?
Ji'nan thermal Co., Ltd., the responsible person, said that they would want to apply for heat sources from the neighboring yellow station power plant to give them heat first, but the heat source is limited. "Hengda city and Vientiane new sun may be warmer next January." The person in charge said. In the future, they will also prepare alternate heat sources, such as the Tang Ye heat source plant, which will be built soon. Once the area suffers from insufficient heat sources, residents do not have to worry about stopping heating.