JiNan Railway Station North Square Construction timetable, German designers rebuild old railway station
February 27th news (reporter Zhang Jie Intern Wang Yanyan Jiang Xiao) the planning and construction of the north square of JiNan Railway Station In February 27th, the reporter learned from the office of the Construction Command Department of the north square of the railway station that the project was designed to discharge the timetable.
the planning and construction meeting of the north square of the railway station, held in January 29th, clarifies the work and technical division of responsibility and the organization of the work organization, which is responsible for the old city development investment group of the design main body of the north square of the railway station; the technical organization is responsible for the city planning bureau and the City Planning Institute. The city planning institute takes the lead in coordinating and coordinating the design consortium of three design units in Shanghai municipal hospital, Shanghai modern and iron courtyard, and the plan design work is carried out. The first round of the first round of 2-3 planning and design plans is put forward by the coordination design union of the City Planning Institute before March 15th, in order to carry out the research and selection.
according to the subsequent work plan, in early March, the old city development investment group and the City Planning Bureau organized a design unit for a docking to ensure the feasibility and integrity of the scheme. In March 4th, the German Hubert designer came to discuss the design of the old train station reconstruction plan, and started the reconstruction work of the old railway station.
March 15th around the initial design of the audit, to further improve the program. At the end of March, the design of the project was completed. At the beginning of April, the project of the north square of the JiNan Railway Station was submitted to the north square of the railway station to study the construction of the command department of the north square of the railway station.
completed the partial expansion plan design of JiNan Railway Station North terminal in late April. At the end of May, the design of the construction map of the North Station of JiNan Railway Station is completed. At the same time, the design plan of the Northwest Station and the planning conditions of the project are determined. In the early June, the construction bidding and construction work was organized to strive to start construction at an early date. Since the implementation of
North Railway Station integration project, all circles of the society have paid close attention to it. The main leaders of the city of Ji'nan examined the scheduling situation, studied the plan, solved the problems, and negotiated with the Ministry of Railways and the Ji'nan Railway Bureau, and achieved great support from the railway department. Next, the Command Office of the North Plaza of the railway station will work hard with the relevant departments to intensify the work and strive for the early integration of the north station.