Ji'nan set up Xiaoqing River pollution control "military order" next year, the overall quality of the exit section reaches the standard.
source: Ji'nan times Author: Zhao Lu
"water pollution control is the same as big gas pollution control, very important." In May 2nd, the Municipal Committee of the Standing Committee of the municipal Party committee and Zhang Haibo, the deputy mayor of the Municipal Committee of the municipal Party committee of the city of Xiaoqing River, stressed that "we should focus on the time node and carry out the task of water pollution control." This is a 'military order'. In order to solve the "water problems" such as insufficient capacity of urban sewage treatment, mixed pollution of rain and sewage, and direct discharge of domestic sewage, the "action list" for water control was released.
[problem 1:]
solution
wastewater treatment plant
the completion time before the end of June 2018 / > in recent years, the pollution control of Xiaoqing River has been strengthened further, and the water quality has been obviously improved, but there is a big gap with the "water ten" requirements. In April 17th, the executive meeting of the municipal government examined and passed the action plan for the action of pollution control and harnessing in the Xiaoqing River Basin, which required the water quality of the Luohe Xia Hou bridge section and the Xiaoqing River section to reach the grade V standard in 2017, and the water quality of the Xiaoqing River in the Xiaoqing River in 2018 reached the grade V of the surface water.
sewage produced by tributaries will be imported into the Xiaoqing River, making it overburdened. In order to solve this problem, in accordance with the requirements, the Tianqiao plan to complete the relocation of the urban sewage treatment plant on the west side of the present site of the Guangda water plant before the end of September 2017. By the end of June 2018, the Municipal Public Utility Bureau has completed the project construction and application of the first and two plant expansion projects (100 thousand tons / day). In addition, according to the construction of the water purification plant (40 thousand tons / day) of the La Shan area in accordance with the city control site, the city municipal public bureau completed the construction of the project before the end of September 2017 and completed the project construction before the end of June 2018. In the later period, the Municipal Public Bureau reconstructs a 100 thousand to 200 thousand ton in the south of the Xiaoqing River and the west side of the Beijing Fuzhou Expressway. The daily scale of urban sewage treatment plants will solve the problem of new sewage and the Emei area sewage treatment.
sewage treatment plant is also in the process of pollution control. Municipal public utilities is responsible for the reform and improvement of sewage pipelines and the construction of sewage pumping stations. Before the end of 2017, the city Guangda water plant is connected to the two, one and three plants.
[problem 2:]
solution
31 black and stinky water bodies "deodorizing"
completion time at the end of December 2017
request to speed up the control progress of the black and smelly water body in the built area. Before the end of this year, 31 black and odorous water bodies in the urban area were basically completed, and the black and odorous water bodies were controlled within 10%.
black and odorous water treatment is defined responsibility unit. Mainly by the relevant district government, Ji'nan City Construction Investment Group Co., Ltd., Ji'nan Old City Development Investment Group Co., Ltd., Xicheng group, Riverside group respectively. The commencement time is 2016, and it needs to be completed before December 2017.
in speeding up the construction of decentralized sewage treatment facilities, the city should complete the demolition work of the Dajian sewage treatment station (20 thousand tons / day) before the end of June 2017, and the Municipal Public Bureau will complete the project construction and invest before the end of June 2018. Licheng completed the construction of Zhao Wang River water treatment station (3 thousand tons / day) by the end of 2017. Ji'nan Binhe New Area Construction Investment Group Co., Ltd. will finish the construction of Huashan water purification station (30 thousand tons / day) by the end of June 2018. Municipal Public Bureau is responsible for speeding up the upgrading of the 11 decentralized sewage treatment stations in the urban area, and completed 9 reforms before the end of June 2017 and completed by the end of October 2017.