Ji'nan intends to introduce 20 million long Yangtze River east line Shandong section to start diversion.
8 days, the reporter learned that the East Route of the south to north water transfer to the first phase of Shandong began to adjust water, from 2015 to 2016 of the annual plan to be transferred to 602 million cubic meters of water in Shandong. Among them, Ji'nan will adjust the Changjiang water 20 million cubic meters in this year, and will adjust the water source at the right time according to the overall scheduling situation in Shandong province. After the Spring Festival, the Changjiang River can be transferred into the Yuqing lake reservoir or the supine Hushan Reservoir through the construction of the water transportation route required by the south to North Water Transfer Project of Ji'nan city.
the first phase of the Shandong section of the East Route of the south to North Water Transfer Project, after 11 years of construction, completed the main construction task of the main line at the end of 2012, and passed through the test of water and trial operation, and turned into the official operation in November 15, 2013. Previously, the Shandong section of the south to North Water Diversion Project has successfully implemented three water circulation of two water diversion years from 2013 to 2014, 2014 to 2015. The project is in a safe and stable state, and the water quality of the trunk line reaches the standard of the surface water of three types.
in accordance with the water transfer plan, in January 8th, the Taierzhuang pumping station of Zaozhuang first opened the machine, from Jiangsu river water into Shandong, water diversion through the Han Zhuang canal into the Nansi Lake to Zaozhuang and Jining, and the Liang Ji canal, Liu Changhe into the East Pinghu. After the water supplement for two lakes, it is divided into two roads, one way to the East through the Jiaodong trunk line to Ji'nan and Zibo, and the joint operation with the Jiaodong water transfer project to Weifang, Qingdao and Weihai. The other way is to plan to go north to the Yellow River in the early May and supply water to Dezhou through the north route of Shandong Province. The water diversion lines will pass through 13 cities in the whole province, with a total length of more than 1300 km.
according to the introduction, after the Shandong section is officially opened to water, it can provide water resources for Ji'nan, Qingdao, Zibo, Zaozhuang, Dongying, Yantai, Weifang, Jining, Weihai, Dezhou, Liaocheng, Binzhou, 58 counties (districts) to provide water resources to alleviate the shortage of water resources. After deducting the loss of water along the line, the water supply will be 242 million cubic meters to 8 cities in Zaozhuang, Jining, Dezhou, Ji'nan, Zibo, Weifang, Qingdao and Weihai, and 200 million cubic meters of water for the South four lakes and the East Pinghu. The water transfer will continue to run until the end of May.
at present, the part of the south to North Water Diversion Project in Ji'nan has been completed and ready to meet the Yangtze River water at any time. Using the Yuqing Lake diversion project, the Yangtze River water can be introduced into the reservoir for domestic water. Using the water diversion project of Yufu River Reservoir in Yufu River, Changjiang River can be transferred into the reservoir of supine tiger mountain, which can be used for various kinds of water for ecology, life and production. In the case of drought in Ji'nan in the last two years, it can effectively alleviate the shortage of water resources and supplement the water source for Ji'nan.