Since the official start of the new reserve warehouse and renovation of the supporting housing project of Jinan Emergency Material Reserve Base on August 23 this year, the work team has taken the performance appraisal target as the general starting point and led the participating units to scientifically formulate the construction plan to ensure that the important nodes of the project are completed on schedule.
济南市应急物资储备基地新建储备库及改造配套用房项目于今年8月23日正式开工以来,工作专班以绩效考核目标为总抓手,带领各参建单位科学制订工期计划,确保工程重要节点按期完成。

The Jinan Emergency Management Bureau has grasped all kinds of formalities to ensure that all kinds of sub-project demonstration and acceptance work are completed as scheduled. And scientifically organize the construction, carry out the construction of each sub-item, prepare materials in advance, prepare in advance, enter the structural construction stage, take advantage of the favorable weather, and seize the construction period by increasing the working surface.
济南市应急管理局抢抓各类手续办理,确保各类分项论证、验收工作如期完成。并科学组织施工,各分项施工压茬进行,提前准备材料、提前进场准备,进入结构施工阶段,利用利好天气,采取增加作业面等方式抢抓工期。

In addition, the construction unit is dispatched in a unified manner, and all participating units cooperate closely to summarize and analyze the fund payment nodes and amounts, and do a good job in fund application in advance to escort the smooth development of the project.
除此之外,建设单位统一调度,各参建单位密切配合,对资金支付节点及金额进行汇总分析,提前做好资金申请工作,为项目顺利开展保驾护航。

The reporter learned that up to now, the raft concrete pouring has been completed, and the main structure construction below ±0.00 is underway, and it is planned to complete the construction of the main structure below ±0.00 by the end of November, and the construction of the main structure of the first floor will be completed at the end of December. The overall project is expected to be delivered in April 2024.
记者了解到,截至目前,正筏板混凝土浇筑完成,正在进行±0.00以下主体结构施工,计划11月底完成±0.00以下主体结构施工,12月底完成一层主体结构施工。整体项目预计2024年4月份交付使用。

前篇:天桥区举办道德模范与身边好人先进事迹宣讲... 后篇:艾山街道深入开展铁路沿线环境整治工作,确...
发表我的评论


推荐文章   因救母失去双腿,农村女孩4小时爬行8公...   司机与出租车公司是劳动关系吗? 济南中...   济南15处免费避暑胜地   安徽29岁偏瘫教师回课堂:感谢母亲,想...   盲女心医:16年免费为2000人做心理援助
随机文章   Jinan foreign talent green channel, ...   Jinan, overseas tourists can leave t...   Drought in Ji'nan city   April Ji'nan, catkin like snow   Spring in Ji'nan is here
广告

其他推荐

因为本站所有内容均转载自其它媒体,本意为公众提供免费服务,但并不代表本网赞同其观点,也不能对其真实性验证负责,如稿件版权单位或个人不想在本网发布,请与我联系,本人会立即将其撤除,谢谢.联系方式:atseashawk@163.com QQ:99289555